Construction FAQ

 

Frequently Asked Questions

When will project begin?
June 15th - 11th Ave & Mallory St
July 6th - 12th Ave closes down between Mallory & Moreno

Why are we doing this and what will the project accomplish?
A more cohesive campus between the Cathedral & Sacred Heart Cathedral School and additional classrooms to serve the community.

Road construction: New sidewalk entry plazas and tree canopy at street corners to shorten crosswalks and increase safety, new bump outs to protect parking and reduce pedestrian exposure to traffic, angled parking spaces and street trees to create edge friction, slowing down vehicular traffic along 12th Ave.

Classroom construction: Four new classrooms will sustain the academic rigor our families expect, reduce overcrowding, and open our doors to families who are actively seeking a Catholic education for their children.

How long will the project last?
Road construction phase &12th Avenue road closure - approximately 10-12 weeks
Classroom phase will begin in August and take approximately 10-11 months to complete

What is the scope of the project?
This project will occur as a multi-phase vision. Phase 1: The New 12th Avenue Experience, Phase 2: Classroom Additions and Future Phase: School Gym.

What trees will be removed?
No Legacy Oak trees will be harmed during any phases of our construction. The fenced off trees will NOT be removed.
Four new oak trees will also be added to 12th Avenue.

What will the detour pattern be while 12th Avenue is closed?